Period
2007–2013
Client
Iran Power Development Organization
Location
Abadan city
Stage
Installation, testing, and commissioning
Technical Specifications
- DCS-type substation
- Ring arrangement with four breakers, convertible to 1½ breaker scheme
- Includes:
- Two 400 kV line feeders
- Two steam power plant unit feeders
- Construction of a short interconnecting line between two power plant units and new feeders
Moshanir responsibility:
Moshanir was responsible for:
- Preparation of tender documents
- Organizing tenders and contracting with suppliers/contractors
- Design review (electrical and civil)
- Site supervision during installation and commissioning
- Oversight of provisional and final handover
Key Achievements
- First 400 kV substation in the region, significantly enhancing transmission capacity and grid reliability