Period
2007–2013
Client
Iran Power Development Organization
Location
Iraq – Cities of Karbala and Najaf
Stage
Final delivery
Technical Specifications
• The project includes:
o Two fixed substations at 33/132 kV (Karbala and Kufa)
o Four substations at 11/33 kV (Qods, Al-Jami’ah, Maysan, and Al-Askari)
• 33/132 kV substations:
o Four 132 kV line feeders
o Three 33/132 kV transformer feeders with double busbar arrangement
o Eleven 33 kV outgoing feeders
o Three capacitor bank feeders
o Three 0.4/33 kV transformer feeders
• 11/33 kV substations (each):
• Two 33 kV cable line feeders
• One bus coupler
• Two 11/33 kV transformer feeders
• Eight 11 kV outgoing feeders
• Two 0.4/11 kV transformer feeders
Moshanir responsibility:
Moshanir was responsible for:
• Preparation of tender documents
• Organizing tenders and contracting with contractors
• Design review
• Site supervision
• Oversight of provisional and final handover of substations
Key Achievements
• Strengthened Iraq’s transmission and distribution infrastructure in Karbala and Najaf regions
• Successful delivery of multiple substations with modern double busbar arrangements
• Enhanced reliability and capacity of the Iraqi power grid through international cooperation