Period
2006–2013
Client
Sistan & Baluchestan Regional Electricity Company
Location
Zahedan – Kilometer 10, Iranshahr Road
Stage
In operation, pending provisional handover
Technical Specifications
• Busbar arrangements:
o 400 kV: 1½ breaker scheme, four-breaker ring
o 230 kV: double busbar arrangement
• 400 kV feeders: two line feeders and two transformer feeders
• 230 kV feeders: two transformer bays + one Extension bay, six line feeders + four Extension feeders, one coupler feeder
• Two shunt reactors and two neutral reactors
• Two 315 MVA power transformers
• Substation control system: DCS
Moshanir responsibility:
Moshanir provided:
• Engineering services (Phases I, II, III-a, and III-b)
• Site supervision of civil works and equipment installation
Key Achievements
• First 400 kV substation in the region, significantly strengthening transmission capacity and grid reliability in Sistan & Baluchestan