Abadan Combined Cycle Power Plant

Abadan Combined Cycle Power Plant

Period 2007–2016
Client Thermal Power Plants Holding Company (Iran Power Development Organization)
Location Kilometer 9, Abadan–Mahshahr Road
Stage Commissioned and permanently delivered

Technical Specifications

•    Composed of 4 gas turbine units and 2 steam turbine units
•    Total installed capacity: 820 MW
•    Primary fuel: natural gas
•    Secondary fuel: diesel oil
•    Cooling system: Air-Cooled Condenser (ACC) type

Role of Moshanir Company

Moshanir provided engineering and overall supervision services, including design review and adaptation, supervision of domestic equipment manufacturing, project management and control, and site supervision.

Key Achievements

•    Enhancement of national grid generation capacity
•    Strengthening domestic manufacturing capability for major power plant equipment