Period
2017–2021
Client
Khorramabad Power Generation Company
Location
Southeast of Khorramabad, Andimeshk Ring Road
Stage
The first gas turbine unit of the plant was synchronized with natural gas fuel on February 16, 2020 at 17:05.
Technical Specifications
• Project consists of one combined cycle block including:
o Two gas turbine units, each rated at 162 MW
o One steam turbine unit rated at 160 MW
• Total installed capacity: 484 MW (Class E)
• Cooling system: Air-Cooled Condenser (ACC)
• Heat Recovery Steam Generator (HRSG): dual-pressure type with supplementary firing system
Role of Moshanir Company
Moshanir provided engineering and overall supervision services, including design review and adaptation, supervision of domestic equipment manufacturing, project management and control, and site supervision.
Key Achievements
• Strengthening the regional power grid of Lorestan Province
• Supplying electricity to infrastructure and developing industries in the region
• Contributing to local employment opportunities